Peripheral Crate Electronics
Testing,
Installation and Commissioning Procedures
1 Receive and Store
1.1 Receive
Boards
1.2 Store
Boards
2 Crate
Electronics Test –
2.1 Crate
2.2 Install
boards
2.3 Perform power test of loaded crate
2.4 Stage
boards for transfer to SX5
3 Crate Installation Test
------------------------------------------------------------------------------
1 Receive
and Store
1.1 Receive
Boards
1.1.1 Unpack
checking for damage
1.1.2 Check
board ID against shipping manifest
1.1.3 Enter
board ID into Electronics db
1.1.4 Enter
board ID into Electronics Log
1.2 Store
Boards
1.2.1 Repack
the boards into the shipping box and place on proper area of storage shelves
1.2.1.1 TBM
& RAT boards > Repack into smaller inner box and discard outer larger
box and bubble wrap
1.2.2.2 All
other board types > repack into original boxes
------------------------------------------------------------------------------
2 Crate
Electronics Test – To be completed at ISR
2.1 Crate
2.1.1 Install
complete empty crate in test stand
2.1.2 Connect
2.1.3 Connect
chiller to CRB and HE
2.1.4 Perform
power up test on empty crate
2.2 Install
boards
2.2.1 Make
sure crate
2.2.2 OSU
CC
Perform Visual Inspection of board prior to installation in crate
Check the switches and fuses on each board
prior to loading.
Install in crate
Add to installed list on program
2.2.3 MPC
Perform Visual Inspection of board prior to installation in crate
Check the switches and
fuses on each board prior to loading
Install in crate
Add to installed list on program
2.2.4 CCB
Perform Visual Inspection of board prior to installation in crate
Check the switches and
fuses on each board prior to loading
Install in crate
Add to installed list on program
2.2.5 DMB Visual
Inspection and mechanical corrections –
Perform Visual Inspection of board prior to installation in crate
2.2.5.1 Labeling
- The DMB do not have a serial number on the front panel. Labels must be made and attached to the front
panel of each DMB.
2.2.5.2 Inspect
and Correct press fit pin guide at back of board – On many boards either or
both of the press fit pin guides are not pushed in fully. Check each board for properly pressed in
guides. When there is a gap between the
guide and the board surface the guide must be pressed completely into the board. To do this use a large channel lock
pliers. Place the pliers over the rear
of the board so that it presses on the top of the guide and the outside of the
board under the guide. Squeeze firmly to
press the guide into contact with the board surface. Then tighten the Philips head screw that is
also on the guide.
Check the switches and
fuses on each board prior to loading
Install in crate
Add to installed list on program
2.2.6 TMB Visual
Inspection and mechanical corrections –
Perform Visual Inspection of board prior to installation in crate
Check the switches and fuses on each board
prior to loading
Install in crate
Add to installed list on program
2.2.7 RAT
Visual Inspection –
Perform Visual Inspection of board prior to installation in crate
Check the switches and fuses on each board
prior to loading
Install in crate
Add to installed list on program
2.3 Perform
power test of loaded crate
2.3.1 Run Startup program on CRB
2.3.1 Run Electrical tests on crate
2.3.1.1 Read
LV values for each board – make sure they are OK
2.3.1.2 Check
firmware version for each board – Update as necessary
2.3.1.3 Run
all other tests
2.4 Stage
boards for transfer to SX5
2.4.1 Record
slot versus board ID so that boards can be installed in same slots at SX5 they
were tested in.
2.4.2 Remove
boards and pack into boxes
2.4.3 Label
boxes and move to staging area to await pick up and transfer.
------------------------------------------------------------------------------
3 Crate
Installation Test
The test fixture at SX5 consists of a control PC and temporary LVPS
for both the PC and its related 9 CSC’s.
The only IO to the crate is a single optical fiber from the computer to
the CC.
3.1 Crate
3.1.1 Install
complete empty crate in target rack
3.1.2 Connect
3.1.3 Connect
water hoses to CRB and HE
3.1.4 Perform
power up test on empty crate
3.2 Install
boards
3.2.1 Make
sure crate
3.2.2 OSU
CC
Perform Visual Inspection of board prior to installation in crate
Check the switches and
fuses on each board prior to loading
Install in crate
Add to installed list on program
3.2.3 MPC
Perform Visual Inspection of board prior to installation in crate
Check the switches and
fuses on each board prior to loading
Install in crate
Add to installed list on program
3.2.4 CCB
Perform Visual Inspection of board prior to installation in crate
Check the switches and fuses on each board
prior to loading
Install in crate
Add to installed list on program
3.2.5 DMB Visual Inspection and mechanical
corrections –
Perform Visual Inspection of board prior to installation in crate
Check the switches and fuses on each board
prior to loading
Install in crate
Add to installed list on program
3.2.6 TMB Visual Inspection and mechanical
corrections –
Perform Visual Inspection of board prior to installation in crate
Check the switches and
fuses on each board prior to loading
Install in crate
Add to installed list on program
3.2.7 RAT
Visual Inspection –
Perform Visual Inspection of board prior to installation in crate
Check the switches and fuses on each board
prior to loading
Install in crate
Add to installed list on program
3.3 Perform
power test of loaded crate
3.3.1 Run
Startup program on CRB
3.3.1 Run
Electrical tests on crate
3.3.1.1 Read
LV values for each board – make sure they are OK
3.3.1.2 Check
firmware version for each board – Update as necessary
3.4 Connect
skew clear cables to crate
3.4.1 Connect skew clear cables to each board
3.4.2 Adjust and move slack in cables to redress after connections
3,5 Conduct crate plus chambers tests
------------------------------------------------------------------------------